CAA Title V Petitions in EPA's South Central Region
Title V allows the public to petition the EPA Administrator to object to specific permits or operating permit program deficiencies when it has provided timely comment to the permitting authority during the public review period. Below are petitions, responses and other documents received during the Title V Operating Permit Program petition process. Petitions submitted to EPA undergoing a 45 day review, including the start and expiration dates for EPA's 45 day review period, and the start and expiration dates for the public's 60 day petition period.
State/Permitting Authority | Facility | Petitioner | Permit Number | Date Petition Received | Status/Comments |
---|---|---|---|---|---|
LA | Cheniere Energy Sabine Pass LNG Liquifaction | Gulf Coast Environmental Labor Coalition (GCEC) | Title V permit 0560-00244-v3 | 2/3/2012 | Acknowledge receipt of petition: 3/5/2012 |
LA | Murphy Oil/Meraux Refinery | LEAN/ Sierra Club, et al. | Title V permit 2500-00001-V5 | 12/10/2009 |
NOI to Sue LDEQ Resp to Order: 12/20/12 The final order denying the petition was signed on May 29, 2015 |
LA | Yuhuang Chemical Inc. – Methanol Plant, St. James Parish | Sierra Club and the Louisiana Environmental Action Network (LEAN) | Title V Permit No. 2560-00295-V0 | May 19, 2015 | The final order granting in part and denying in part the petition was signed on August 31, 2016. |
LA | Bunge North America - Grain Elevator | Cynthia Portera, Toni Offerman, Tulane Environmental Law Clinic | Title V Permit No. 2520-00048-V5 | Jan 16, 2016 | Pending |
AR | Entergy Arkansas, Inc - Independence Plant | Sierra Club | Title V permit 0449-AOP-R7 | Oct 19, 2010 | Pending |
AR | Entergy Arkansas, Inc – White Bluff | Sierra Club | Title V permit 0263-AOP-R7 | Jan 28, 2010 | Pending |
AR | Big River Steel, LLC | Nucor Steel – AR And Nucor-Yamato Steel | Title V permit 2305-AOP-R0 | Oct 9, 2013 | Pending Acknowledge receipt of petition: 11/1/13 |
AR | Entergy Arkansas, Inc – White Bluff Power Plant | Sierra Club | Title V Permit No. 0263-AOP-R8 | May 6, 2015 | Pending - Acknowledgement letter for receipt of petition: 05/12/2015 |
AR | Entergy Arkansas, Inc – Independence Power Plant | Sierra Club | Title V Permit No. 0449-AOP-R8 | May 5, 2015 | Pending - Acknowledgement letter for receipt of petition: 05/08/2015 |
TX | Shell Deer Park Chemical Plant | EIP | Title V permit O1668 | May 19, 2014 | |
TX | Shell Deer Park Refinery | EIP | Title V permit O1669 | May 19, 2014 | |
TX | Southwestern Electric Power Company (SWEPCO) H.W. Pirkey Power Plant in Harrison County, Texas | EIP | Title V permit O31 | Oct 30, 2014 |
|
TX | Dow Chemical Company's Freeport Salt Dome facility | Environmental Integrity Project, and Sierra Club | Title V Permit No. O2212 | Aug 31, 2015 | Pending |
TX | ExxonMobil Corporation – Baytown Olefins Plant, Harris County, TX | Environmental Integrity Project, Sierra Club, and Air Alliance Houston | Title V Permit No. O1553 | Aug 8, 2016 |
|
TX | Motiva Port Arthur Refinery | EIP, Sierra Club, and Air Alliance Houston | Title V Permit O1386 | Dec 20, 2016 | Pending |
TX | Flint Hills Resources Corpus Christi East Refinery | EIP and Sierra Club | Title V Permit O1445 | Nov 29, 2016 | Pending |
TX | Southwestern Electric Power Company (SWEPCO) - Welsh Plant | EIP and Sierra Club | Title V Permit O26 | Nov 8, 2016 | Pending |
TX | Pasadena Refinery | EIP, Sierra Club, Texas Environmental Justice Advocacy Services, and Air Alliance Houston | Title V Permit O3711 | Nov 8, 2016 | Pending |