Underground Injection Control (UIC)

Public Notice: Proposed Permit Modification for ADM Class VI Well in Decatur, Ill.

Publish Date: 11/10/2016

Summary

U.S. EPA plans to modify a permit for an injection well owned by the Archer Daniels Midland Company, 4666 Faries Parkway, Decatur, Illinois.

The existing permit is for one injection well, CCS#2, that ADM wants to use to inject and store carbon dioxide, or CO2, underground. The CO2 is created when ADM makes ethanol. ADM plans to inject 1.1 million metric tons of CO2 per year into this well over five years. EPA first issued this permit in 2014.

The proposed modifications will update the permit and attachments because of new information obtained during well construction and pre-injection testing. Only the conditions proposed for modification are re-opened for comment. A detailed list of the proposed modifications is available on EPA’s website, at the Decatur Public Library, or by contacting EPA.

Applicant or Respondent

Archer Daniels Midland Company
4666 Faries Parkway
Decatur, IL

Permit #: IL-115-6A-0001


Related Documents

You will need Adobe Reader to view some of the files on this page. See EPA’s About PDF page to learn more.