Report #08-2-0226, August 6, 2008
What Was Found
The grantee claimed $2,385,634 for pre-award costs under Grant XP98237601 that were incurred prior to the grant award and thus were unallowable under the grant administrative conditions and Office of Management and Budget Circular A-87.