Initiate deactivation of K West Reactor Basin

12/31/2019 (12/31/2015)

M-093-28

Submit a change package for proposed interim milestones for placing K East and K West Reactors in Reactor Interim Safe Storage

12/31/2019 (12/31/2015)

M-016-173

Select K Basin sludge treatment and packaging technology and propose new interim sludge treatment and packaging milestones

9/30/2022 (3/31/2015)

M-016-181

Complete deactivation, demolition & removal of K West Reactor Basin

9/30/2023 (9/30/2019)

M-016-186

Initiate soil remediation under K West Reactor Basin

12/31/2023 (12/31/2019)

M-016-143

Complete the interim response actions for 100 K Area within the perimeter boundary and to the Columbia River for specific waste sites and facilities.

9/30/2024 (12/31/2015)

M-093-27

Complete K East Reactor and K West Reactor Interim Safe Storage in accordance with the Removal Action Work Plan

9/30/2024 (12/31/2019)

M-016-00C

Complete all response actions for the 100 K Area


9/30/2024 (12/31/2020)