Hazardous Waste Cleanup: Fareva Richmond Incorporated (Formerly: Pfizer Health Care) in Richmond, Virginia

On this page:


Pfizer, through legacy Wyeth, entered EPA's Region 3's Resource Conservation and Recovery Act (RCRA) Corrective Action "Facility Lead Program" in September 2006 to meet RCRA Corrective Action obligations associated with the former operation of a hazardous waste storage area. The Facility Lead approach was used by EPA Region 3 to streamline the administrative process and initiate investigations at RCRA regulated facilities more quickly. Previously, the facility was enrolled in the Virginia Voluntary Remediation Program (VRP) to address releases of various constituents to groundwater from the Former Plant A and its associated wastewater treatment plant at the facility. Entry into the Facility Lead Program broadened the geographic scope of the release assessment to the entire RCRA Facility. Pfizer sold the facility to Fareva in the Fall of 2011.  Fareva continues to operate the facility and Pfizer continues to implement RCRA Corrective Action investigations under the Facility Lead Program with oversight by EPA.

Cleanup Status

The environmental indicator for current human exposures under control was achieved in September 2014. The environmental indicator for migration of contaminants in groundwater is under control was achieved in April 2016. Information continues to be being gathered and reviewed to determine whether sufficient data has been gathered to support a remedy decision. A remedy decision is expected within two years.

Cleanup Background

In 1992, a release to the ground of flea dip product from a vent pipe on the west wall of the Former Plant A was discovered. Impacted soil was excavated and disposed of off-site in two phases. In April 1993, soil extending approximately 8 feet west from the west wall of the former Plant A and three feet deep was excavated. In August 1993, soil extending approximately ten feet by 35 feet along the west wall to a depth of ten to 12 feet was excavated.

Following soil excavation, a 10,000 gallon underground storage tank which formerly contained isopropyl alcohol was removed from the area, and the area was backfilled, leveled, and compacted.

During the early 1990’s, a break in an underground process sewer line at the former Plant A waste water treatment plant was discovered and repaired.

In the late 1990’s, floor drains in the Plant B former Train Shed were connected to a sewer system. Prior to the connection, floor drains in the shed discharged to the subsurface soil. (Notified to EPA in early 2014.)

In 1998, the main process sewer located north of Plant B and Building 2300 and on a west to east line parallel with Darbytown Road- continuing east to South Laburnum Road -was found to be compromised in proximity to Cornelius Creek. A new sewer line was installed along where the piping was compromised. An abandoned sewer line remains in place.

Approximately in the early 2000’s, a brick lined sump receiving waste directly from the main sewer line overflowed near Cornelius Creek. Investigations of this area were initiated in 2008.

In 2001, the former Plant A, including the former Plant A waste water treatment plant, was demolished. In addition, sewers associated with the former Plant A were excavated and removed. During the demolition and removal activities, impacted soils were encountered. Impacted soils by the former Plant A waste water treatment plant were excavated. Soil samples were collected throughout the demolished Plant A area, including by the flea dip excavation area and by the former waste water treatment plant area. Throughout the investigation, field meters indicated that the level of volatile organic chemicals was elevated. The analyses results showed that the concentrations of chemicals which were analyzed for and detected are below screening criteria applied to soils at industrial facilities.

An investigation of impact to groundwater was conducted. Initial results detected elevated levels of contaminants in groundwater in the area of former Plant A. Subsequent investigations have been conducted to determine the nature and extent of the groundwater contamination. Contamination has been found in groundwater extending east and southeast of Building 2300 and extending to the southeast property boundary on Darbytown Road. A long-term groundwater monitoring program was initiated in 2007. Since 2007, groundwater monitoring wells have been installed throughout the site in the path of the plume to observe constituent concentration trends and the extent of groundwater impact. In January 2012, two groundwater monitoring locations on the southeast portion of the FAREVA property were added to the monitoring program. The level of contamination in groundwater continues to be monitored in the long-term monitoring program.

In 2001, an upstream extension to the main sewer line (AOC 4/5) that runs beneath Plant B was determined to be degraded and required replacement. Plant production was halted, the degraded sewer was line was excavated, and visibly impacted soils were excavated and disposed at an off-site facility. (Notified to EPA in early 2014.)

Additionally in 2001, after finding significant breaks, a sewer line extending north beyond the rear of the Plant B structure was replaced. Abandoned sewer line remains in place.

In 2002, oil was released from a utility building when a gauge broke. Impacted soil was removed to a depth of two to three feet below the ground surface and a temporary sump was installed to collect additional fuel drainage. Soil confirmation samples following the excavation showed that the level of total petroleum hydrocarbons was below 100 parts per million. Virginia Department of Environmental Quality (VADEQ) has issued a closure letter for the release.

In September 2005, approximately 20 feet of the main process sewer line carrying both sanitary and process water located north of Plant B and Building 2300 experienced a break. The line was repaired and the ground was treated with lime.

A survey conducted in early 2006 identified further areas of compromised piping. Additionally it was noted that the main process sewer line located north of Plant B and Building 2300 running for 1/3 mile on a west to east line parallel with Darbytown Road- continuing east to South Laburnum Road experienced a number of breaks and spot repairs over 18 years. As a result, Wyeth installed approximately 2000 linear feet of new sewers. Abandoned sewer line remains in place extending to Laburnum Avenue.

Around the same time period, a sewer at the former Denorex® mixing area on the west side of Plant B was found to be compromised.

In 2008 and in 2009, investigations were conducted by Pfizer to identify releases at the Facility. The locations which were sampled included sediment in Cornelius Creek, a soil and groundwater where the waste water sump overflowed by the Creek [Area of Concern (AOC) 1], soil and groundwater proximate to where breaks had occurred in the main sewer line that extended from north of Plant B to northeast of Building 2300 (AOC 4/5), groundwater locations downgradient of the former Denorex® mixing area on the west side of Plant B, a subsurface tank that had received process sewer overflow from the former Denorex® mixing area, and subsurface soil throughout the Laburnum Avenue Farm Field. At sampled locations along or by the sewer line breaks (AOC 4/5), several constituents were detected in soil. No constituents identified in soil exceeded screening criteria. At sampled locations in Laburnum Avenue Farm Field, several constituents were detected in soil. No constituents identified in soil exceeded screening criteria. At sampled locations downgradient of the former Denorex® mixing area on the west side of Plant B, several constituents were detected in groundwater. No constituents identified in groundwater exceeded screening criteria. These locations continue to be included in the groundwater monitoring program. The contents of the tank that received sewer overflow from the former Denorex® mixing area on the west side of Plant B were found to be impacted. The inside of the tank was rinsed and the tank was filled with concrete and abandoned in place.

At AOC 1 (waste water sump overflow), semi-volatile organic compounds (SVOCs) were detected in soil in exceedance of screening criteria. The SVOCs included bis(2-ethylhexyl)phthalate and 2-methynaphthalene in groundwater and benzo(a)pyrene and dibenzo(a,h)anthracene in soil. The sum of a sub-class of SVOCs, polynuclear aromatic hydrocarbon compounds (PAHs), were elevated in soil. Sediment in Cornelius Creek contained PAHs. The levels of PAHs that were detected in the sediment are within acceptable levels. Groundwater northeast of Building 2300 contained bis(2-ethylhexy)phthalate at levels that exceeded screening criteria. However, bis(2-ethylhexy) phthalate has not been detected in groundwater since three permanent groundwater monitoring wells were installed in the area in 2010.

In 2010, a sub-slab vapor investigation was conducted below the Building 2300. The results indicated there are no current risks to workers in the building resulting from contamination that was detected below the building.

In 2012, surface soil samples were collected at the Laburnum Avenue Farm Field. Several constituents were detected in soil. No constituents identified in surface soil exceeded screening criteria.

In early 2014, Pfizer notified EPA of the potential for release to the environment associated with former forklift maintenance operations conducted at a loading dock adjacent to the rail spur until the early 2000’s. Along with the notification, Pfizer submitted plans to conduct soil sampling at locations surrounding the loading dock.

Top of Page


Site Description

Interactive Map of Fareva Richmond Incorporated, Richmond, Virginia


View larger map

The facility property is comprised of 305.7 acres and is located on the southeast side of Richmond. Two primary buildings currently are located at the facility: Plant B produces and/or packages over-the-counter medications, and Building 2300 operates as a warehouse and sample management laboratory. Past industrial operations at the property include the manufacture of pet pesticide products (flea collars, etc.) and over-the-counter medicinal products (as well as a quality control/quality assurance laboratory) at the Former Plant A, which was constructed in 1975 and demolished in 2001. A distribution center also operated at the property. A farm is located on the eastern portion of the Facility property. The land bordering the property to the north is largely wooded. The surrounding area includes properties zoned for residential, industrial, and agricultural use. A residential development is being constructed immediately south of the facility.

During a RCRA Corrective Action Investigation, solid waste management units (SWMUs) and areas of concern (AOCs) are identified to guide the search for releases. A “Solid Waste Management Unit” is any discernible unit where solid wastes have been placed at any time, irrespective of whether the unit was intended for the management of solid or hazardous waste. SWMUs additionally include any areas where solid wastes have been routinely and systematically released. An “Area of Concern” is any area that is not a SWMU where a spill or release may have occurred. Four solid waste management units (SWMUs) and eight areas of concern (AOCs) have been identified at the RCRA Facility. One of the SWMUs was eliminated as it was incorrectly identified. EPA has provided a letter to Pfizer indicating tentative no further action, pending public review during a future public comment period, for two SWMUs and four AOCs as a result of work completed under the Facility Lead Agreement. Soil, groundwater and vapor investigations have been conducted to identify potential releases and a groundwater monitoring program has been implemented.

Top of Page


Contaminants at this Facility

Contaminants in soil have been detected in the area of the Former Plant A and along abandoned sewer lines.  The levels of contamination that have been identified in sampled soil at those areas do not exceed EPA Region 3 industrial soil screening levels. Contaminants in soil also are present northeast of the Distribution Center in an area where breaks in the sewer occurred (SWMU 4/5) and a former sump overflowed (AOC 1). The primary contaminants of concern are PAHs; however, benzo(a)pyrene is the only PAH that exceeds its industrial soil screening level of 210 µg/kg. Benzo(a)pyrene was detected in surface soil at concentrations ranging from 28-1400 µg/kg. Though most individual PAHs do not exceed screening criteria, total PAHs in soil by the area of AOC 1 are elevated.

Chloroform is the most widespread contaminant detected in on site groundwater; other contaminants detected above screening values include 1,4 dioxane, 1,1,2,2 tetrachloroethane, tetrachloroethylene (PCE), trichloroethylene (TCE) and bis(2- ethylhexyl) phthalate. Current data indicate that the levels of these contaminants in groundwater are either not detected or within acceptable levels throughout the property and at the property boundary.  Data to date indicate a generally decreasing trend in the level of contamination that has been found in groundwater at the Facility.  The maximum chloroform detection in onsite groundwater in October 2014 was 42 µg/L. The maximum contaminant level (MCL) for total trihalomethanes (which includes chloroform) allowed in a public drinking water supply is 80 µg/L. There is no current or projected use of the groundwater for drinking water at the site. Since concentrations of contaminants in groundwater at the property boundary are below applicable screening values and do not appear to be increasing.

Top of Page


Institutional and Engineering Controls at this Facility

It is anticipated that the final remedy will include institutional controls to prevent unacceptable exposures on the portion of the property associated with industrial use.

  Top of Page


Land Reuse Information at this Facility

The property was sold to Fareva, a European-based contract manufacturing company, in the Fall, 2011. Under agreement of the sale, Pfizer retains responsibility for corrective action.

Top of Page


Site Responsibility at this Facility

RCRA Corrective Action activities at this facility are being conducted under the direction of the EPA Region 3 with assistance from the Virginia Department of Environmental Quality.

Top of Page