Fiscal Year 2013 National Priorities List Program Snapshot
- NPL Federal Facilities by Agency
- Status of NPL Federal Facilities
- Regional Percentage Distribution of Fiscal Year 2013 Accomplishments
- Current Site Work
- Completed Site Work
- NPL Federal Facility Site Cleanup Pipeline
- Interagency Agreements
- Institutional Controls at NPL Facilities
- Status of 5 Year Review Protectiveness Statements
- Environmental Indicators at Federal Facilities
- Site Wide Ready for Anticipated Use
- Notes
NPL Federal Facilities By Agency
(Final and Deleted)
![Army: 43 or 25%. DLA: 5 or 3%. Air Force: 37 or 21%. Navy: 54 or 30%. National Guard 1 or 1%. DoE: 21 or 12%. Other 12 or 7%. Corp of Engineers: 1 or 1%.](/sites/production/files/styles/large/public/2014-01/fy_2013_npl_federal_facilities_agency.png)
*Other Federal Agencies include: Coast Guard (1), DOI (2), DOT (1), EPA (1), FAA (1), NASA (2), SBA (1), USDA (2), VET ADMIN (1).
Status of NPL Federal Facilities
NPL Status | Number of Federal Facilities | Number of Private Sites | Federal Facility % of NPL Universe |
---|---|---|---|
Final | 157 | 1,156 | 12% |
Deleted | 17 | 355 | 4.6% |
Total* | 174 | 1,511 | 10.3% |
*Total number of Federal Facilities and private sites on the NPL is 1,676
Regional Percentage Distribution of Fiscal Year 2013 Accomplishments
![RI/FS Start (count – 41). Decision Documents (Count – 70). Final RODs (Count – 4). RA Starts (Count – 40). RA Completions (count – 51_ 5 Year Reviews (Count – 28). Construction Completions (Count -1). Sitewide RAU (Count – 4). Total Categories (Count – 23](/sites/production/files/styles/large/public/2014-01/eoy_2013_npl_regional_percentage_distribution.png)
Current Site Work
![Ongoing Removals: 85. Active TAGs: 15. Ongoing RI/FS Actions: 389. Ongoing RDs: 29. Ongoing RAs: 179. Ongoing O&M: 125.](/sites/production/files/styles/large/public/2014-01/eoy_2013_npl_current_site_work.png)
Completed Site Work
![Removal Comps: 960. Decision Documents: 2,114. RD Comps: 1,028. RA Comps: 1,162. OPS: 54. 5 Year Reviews: 451. Partial Deletions: 24.](/sites/production/files/styles/large/public/2014-01/eoy_2013_npl_completed_site_work.png)
NPL Federal Facility Site Cleanup Pipeline
![NPL Facilities: 174. Facilities with IAGs: 167. Active RABs/SSABs: 116. Final Remedy Selected: 88. All Construction Completed: 72. Deleted Facilities: 17.](/sites/production/files/styles/large/public/2014-01/eoy_2013_npl_pipeline.png)
Interagency Agreements
% of NPL Federal Facilities with Completed IAGs
Federal Agencies that have not achieved 100% of their IAGs/FFAs:
Agency | # w/ IAG | Total # | Percent |
---|---|---|---|
Army | 42 | 43 | 97.7% |
Air Force | 36 | 37 | 97.3% |
NASA | 1 | 2 | 50.0% |
Veterans Admin | 0 | 1 | 0.0% |
Dept. of Agriculture | 1 | 2 | 50.0% |
Dept. of Transportation | 0 | 1 | 0.0% |
SBA* | 0 | 1 | 0.0% |
Agency | # w/ IAG | Total # | Percent |
---|---|---|---|
Navy | 54 | 54 | 100.0% |
Dept. of Energy | 21 | 21 | 100.0% |
DLA | 5 | 5 | 100.0% |
Dept. of Interior | 2 | 2 | 100.0% |
Coast Guard | 1 | 1 | 100.0% |
National Guard | 1 | 1 | 100.0% |
USACE | 1 | 1 | 100.0% |
EPA | 1 | 1 | 100.0% |
FAA | 1 | 1 | 100.0% |
Institutional Controls at NPL Facilities
Remedial Actions and Removal Actions with Institutional Controls
![Remedial Actions: 780. Removals: 44.](/sites/production/files/styles/large/public/2014-01/eoy_2013_npl_remedial_removal_actions.png)
Note: There are 158 NPL Federal Facilities with Institutional Controls.
Status of 5 Year Review Protectiveness Statements
Status of Remedies Requiring Monitoring at NPL Facilities
Total Number of Sites with Completed 5 Year Reviews = 158
(Latest Protectiveness Statement at Site)
![Protective: 65. Will Be Protective at Remedy Complete: 23. Protective in the Short Term: 43. Not Protective: 6. Protectiveness Deferred: 20. Complete: 1.](/sites/production/files/styles/large/public/2014-01/eoy_2013_protectiveness_statements.png)
Note: In the second quarter of FY 2005, EPA implemented a change in the way 5 Year Review data is recorded.
Environmental Indicators at Federal Facilities
EI Status for Final NPL Federal Facilities
(Total Facilities = 174)
![Human Exposure - Controlled: 146. Insufficient Data: 22. Not Controlled: 6. Groundwater - Controlled: 121. Insufficient Data: 26. Not Controlled: 21. Not a GW Site: 6.](/sites/production/files/styles/large/public/2014-01/eoy_2013_npl_environmental_indicators.png)
Note: 65% of Facilities have both Human Exposure and Groundwater controlled; 1% of Facilities have neither Human Exposure nor Groundwater controlled.
Site Wide Ready for Anticipated Use
![Site Wide RAUs: 55.](/sites/production/files/styles/large/public/2014-01/eoy_2013_npl_swrau.png)
Notes
- All data from 11/12/2013 CERCLIS 3.
- NPL cleanup data includes both Superfund and RCRA activity at Superfund Federal Facilities.